Australia’s first large Concentrated Solar Power plant hinges on Glencore terms

Vast Solar’s hybrid Concentrated Solar Power project at the Mount Isa mining town would cut power prices and emissions and offtake talks are «positive,» Craig Wood, CEO of Vast Solar, told Reuters Events. In July, Vast Solar announced it was developing a 50 MW hybrid CSP-PV-gas plant in the mining town of Mount Isa in …

Australia’s first large CSP plant hinges on Glencore terms

In July, Vast Solar announced it was developing a 50 MW hybrid CSP-PV-gas plant in the mining town of Mount Isa in Queensland. The town hosts Glencore’s giant Mount Isa Mines facility where it operates four copper and zinc mines. The A$600 million ($423.7 million) North Western Queensland Hybrid Power Project (NWQHPP) would be Vast …

Abengoa completes first CSP array at giant Dubai project; Q-Energy fund buys 117 MW CSP capacity in Spain

Abengoa completes first parabolic trough array in Dubai Spain’s Abengoa has completed construction of the first of three 200 MW parabolic trough solar fields at the 950 MW Noor Energy 1 CSP-PV project in Dubai, the company announced September 24. Developed by Saudi Arabia’s ACWA Power, the $4.4 billion Noor Energy 1 project will be …

Protermosolar: The international Concentrated Solar Power sector recognizes the professional career of Luis Crespo with the Lifetime Award

The award has been presented at the inaugural session of the SolarPACES 2020 Conference. The Technology Centers and Spanish companies have also awarded the President of Protermosolar with a special award for his commitment to the sector and the achievements obtained. Luis Crespo, president of the Spanish Association for the Promotion of the Solar Thermal …

Can NREL’s Fault-Finding Study Help Concentrated Solar Power?

Concentrated solar power is facing its biggest opportunity in years with an important new tool at its disposal. As Spain considers procuring 5 gigawatts of CSP, the largest amount ever tendered, the sector is looking to avoid mistakes with a highly detailed best-practices guide. The Concentrating Solar Power Best Practices Study, published in June by the U.S. …

Abengoa advances in the construction of the world’s largest concentrated solar power complex in Dubai

The company has just celebrated the completion of the first solar field of the three 200 MW parabolic trough plants which is building in phase IV of the Mohammed bin Rashid Al Maktoum (MBR) Solar Park, in the United Arab Emirates. Its construction has involved the installation and assembly of 2,120 collectors, each weighing 40 …

Cerro Dominador Eyes on More Concentrated Solar Power projects in Chile

Chile has abundant solar resources. The Cerro Dominador project currently under construction is the first commercial CSP station in South America. The power station has an installed capacity of 110MW, with molten salt tower technology and a heat storage system, and can realize 24-hour uninterrupted power generation. The global economy is under the impact of …

Program for the 2020 SolarPACES Conference is Now Online

SolarPACES 2020 is coming up soon; starting Monday, 28th September. We are happy to update you on the latest news and program additions. Conference Program The full program of technical and plenary sessions is now available online. More than 400 contributions in the technical program among oral and poster presentations organized in 16 tracks allow a thorough …

Xavier Lara on How Spain’s Q4 Auction Can Achieve the 5 GW of Concentrated Solar Power it Wants